
Community Recreation Center
Bond program
Bond Kick-off video
As Redmond rapidly continues to grow in population, the new recreational center will provide enhanced facilities to meet the needs of the community and stand as an investment in future generations.
Currently, the Redmond Area Park and Recreation District (RAPRD) administration and activities are hosted at the only public pool in Redmond – the Cascade Swim Center. Opened in 1979, the swim center catered to a population of about 6,500 people in the recreation district. Now, the district encompasses roughly 45,000 people, which has stretched the Cascade Swim Center in capacity with no room for growth in activities.
RAPRD passed a $49M bond in November 2022 to fund the facility.
After the first design phase and based on the actual concepts, the program team realized that adjustments were needed in order to align the project with the budget and maintain the bond commitments.
This construction of a new recreational facility will sit on 10 acres at SW 35th Street and Lava Avenue in Redmond, and is planned to include both a competitive pool and leisure pool, locker rooms, gymnasium, exercise facilities, group fitness rooms, special event spaces, offices and other administrative/support spaces, and more.
The Redmond Area Park & Recreation District project is a crucial investment in the future of the community. It will provide state-of-the-art facilities, modern amenities, and the ability for growth in adding programs and recreational opportunities for generations to come.
Project
Info and updates
New Redmond Regional Recreation Center, approximately 56,000 square feet
- AQUATICS PROGRAM AREAS
- (8) Lane 25 Meter Competition Pool
- 3,815 sq ft Leisure Pool w/ hot tub
- Water Slide
- 1 Meter Diving Boards
- Aquatic Support Spaces – Lifeguards, Storage, Office
- Outdoor Sun deck
- RECREATION PROGRAM AREAS
- Gym – (1) High School court with (2) Middle School cross courts
- On grade Track – 14 laps per mile
- 2800 sq. ft Fitness – includes cardio, circuit, and weights
- (2) 24-30 Person Group Fitness Classrooms
- COMMUNITY PROGRAM AREAS
- Child watch
- Multipurpose/Party Rooms
- 40-Person Classroom
- Teaching Kitchen
- SUPPORT PROGRAM AREAS
- Small lobby
- Views into Leisure pools
- Locker Rooms
- (4) Family Locker Rooms and Lounge
- Admin Area including (6) private offices and 10 open offices
- Conference Room
- Front Desk w/ small food service
General Program Updates
In the month of December, the focus of construction remained on getting all footings and foundations poured for the perimeter of the building, along with the mechanical well. The design and management team have focused on reviewing and returning submittals, responding to RFIs, reviewing schedule updates and performing necessary site visits based on the construction schedule.
December Activities
In December, a lot of the construction continued to center around the process of getting ready to pour and the pouring of concrete. KNCC spent some time re-organizing their pour schedule for production and efficiency, then followed that scheduled. This meant several crews working at once, doing different phases of concrete – rebar, forms, pouring, removing forms – as they work around the perimeter of the building.
This is a major step in preparing for the delivery of the metal building which occurred in mid-December. Along with the concrete, KNCC and HMK continued to meet with the project team – designers, subcontractors, etc. – to make sure that submittals were coming in, RFIs were being responded to, and the sub-contractors were ready for their work for building arrival. The whole project team also sat in on a natatorium pre-construction meeting to remind everyone of some important considerations throughout construction and gave the team an opportunity to flush out any questions regarding process.
Activities Scheduled For Next Period
In January, concrete will continue to be poured for footings around the building while stem walls are poured for the east side in preparation for building delivery midmonth. Once the building arrives, additional focus will be on making sure the inventory is correct and the building parts have a lay down yard where they can be organized in preparation of erection, which will start in February. The design team will continue to review submittals and respond to any RFIs that have come up, while HMK will continue to review schedules, manage consultants, and maintain budgets.
Highlights, Challenges, Solutions
HIGHLIGHTS:
Natatorium Pre-Construction!
CHALLENGE AND SOLUTIONS:
Winter Weather! The first snow occurred in December which didn’t hold up any work but served as a reminder that winter weather is coming. The contractor has utilized blankets to keep concrete warm, building a tent above the pump pit to maintain temperatures, and other various tools to make sure production can still occur while the weather worsens.
community details
- Matt Gilman, Chairman
- Kevin Scoggin, Vice-Chair
- Mercedes Bostick-Cook, Director
- David Rouse, Director
- Lena Berry, Director
- JoAnne Fletcher
- Mitchel Elenich
- Karen Danielson
- Louie Arzaga
- Piper Muoio
- Samuel Bernhisel
- Jan Schweizer
Newsletters
Stay up to date on the latest program updates!
February 2024 – RAPRD – Bond Program Newsletter
March 2024 – RAPRD – Bond Program Newsletter
May 2024 – RAPRD – Bond Program Newsletter
June 2024 – RAPRD – Bond Program Newsletter
August 2024 – RAPRD – Bond Program Newsletter
October 2024 – RAPRD – Bond Program Newsletter
November 2024 – RAPRD – Bond Program Newsletter
December 2024 – RAPRD – Bond Program Newsletter