Bond program

In May of 2023, the Central Curry School District passed a bond of $15 million to repair, renovate, and renew their district properties.

An additional $4 million dollars in matching grant funds have already been pre-approved by the State of Oregon to aid in the renovations.

Most of the district buildings were built in the 1940’s and ’50s, which now require significant renovations. The Central Curry School District Bond Program ensures students have the opportunity to learn in a safe, up-to-date environment, and preserve school facilities as long term assets.

The bulk of the funds will be used for roof/gutter repair, windows, entry doors, interior finishes, new HVAC systems, siding, electrical, and plumbing. In addition to that, funds will be used to improve traffic circulation at both schools, create dedicated secure entrances, and increase the safety of district facilities. Some of the funds will also be used to upgrade athletic facilities and update vocational education space.

Many of those in the community were once kids who passed through the district and ended up living in Gold Beach – so the Central Curry School District bond program is a crucial investment in the future of the community for decades to come. It will provide crucial upgrades, greater security, and the ability for growth in vocational education for students.

Riley Creek Elementary School - Bond Update
Gold Beach Jr|Sr High School - Bond Update

Projects

Info and updates

Bond Update

On behalf of the Central Curry School District, I would like to thank all the voters who responded to the bond measure that was on the May 16th ballot. The unofficial results indicate the bond has passed with a 56% approval rate. We are grateful to our community for investing in our buildings to provide our students and staff with a safe and comfortable school environment at each of our school sites. We celebrate this accomplishment with you and appreciate your continued support.

I want to thank the CCSD School Board and bond planning committee for all the hours of work they put into making this happen. Your vision has been inspiring.

– Eric Milburn, Superintendent
Central Curry School District

Follow HMK through the process

Griffin Construction meets with SĀJ Architecture and the District for the Construction Manager|General Contractor (CMGC) kickoff meeting. Griffin will provide a valuable service during the preconstruction phase of the project. Throughout the design phases, Griffin will conduct a thorough review of the design and offer valuable recommendations to the Project Team. These recommendations will cover aspects such as constructability, material availability, procurement timelines, construction scheduling, and cost estimates. ...

1 1

Completion | The renovation of Jackson County Fire District 5 Station 4 is complete.

The project completed a much-needed seismic retrofit that included a new roof, windows/doors, and exterior siding. The renovations provide the facility with seismic-resisting capability that will enable immediate use in emergency responses following a seismic event. The use of fiber cement siding and masonry details instead of wood will also improve the resiliency of the station during potential wildfires.

Other changes to the station included the conversion of one bay to multi-use with a new shower/restroom that will add capacity for additional personnel during peak wildfire season.

The station is also using four-fold apparatus bay doors that are the first of their kind installed in Southern Oregon. Following the 2020 Almeda Fire that destroyed over 2,500 homes, Jackson County Fire District 5 adopted this style door as a standard for all its stations. The doors are not only more durable and reduce maintenance costs, but they are also much easier to operate during power outages common to catastrophic events.

Upgraded insulation, heating and air conditioning is anticipated to improve firefighter comfort and save operating costs.

Firefighters plan to reoccupy the station in mid-December to early January depending on weather and holiday schedule.
...

2 1

Exploring the ‘Hidden Heart’ of the New Government and Public Safety Building; the concealed systems in the ceilings, where a complex network of pipes, conduits, and HVAC equipment will tirelessly power the new Government and Public Safety Center!

This intricate web of essential systems is organized and skillfully interwoven within the overhead structure, ensuring seamless electricity, water, and climate control throughout the building.

Multiple subcontractors collaborate closely, orchestrating design, ordering materials, coordinating installation schedules, and executing installation.
...

4 0

The Jackson County Fire District 5 Station 4 seismic renovation project reached a significant milestone with the installation of the apparatus bay doors.

Although common in larger districts, these four-fold doors are the first of their kind installed in Southern Oregon. Following the 2020 Almeda Fire that destroyed over 2,500 homes, Jackson County Fire District 5 adopted this style door as a standard for all its stations.

The doors are not only more durable and reduce maintenance costs, but they are also much easier to operate during power outages common to catastrophic events.

The only items remaining are paint touch up and cleaning that will take place in November with Firefighters reoccupying the renovated station in mid-December to early January depending on weather and holiday schedule.

The seismic retrofit project includes a new roof, windows/doors, and exterior siding that should be completed by the fall of 2023 and will make much needed structural upgrades to the station that was originally constructed in 1975.
...