Phoenix Government and
Public Safety
Center Project
The Phoenix Government and Public Safety Center Project consists of the construction of a new combined city facility, replacing the Phoenix Fire Station (JCFD 5 Station 3) that was destroyed by the Almeda Fire in September 2020, and the existing City Hall and Police Station buildings.
Oregon House Bills 5006 and 5202 fund in the amount of $16,338,000 were allocated to construct the building with a $240,000 match comprised of insurance and FEMA proceeds.
The new building will utilize the existing footprint of the City of Phoenix City Hall, Fire Station, and Police Station, while increasing the total square footage to 21,600 through the utilization of a second story. The construction of a 2-story building reduces the footprint of the public safety program while eliminating unnecessary land acquisition costs in contrast to multiple single-story buildings.
Project Completion
Project
Info and updates
- Construct a new combined city facility, replacing the Phoenix Fire Station (JCFD 5 Station 3)
- The new building incorporates the footprint of the City Hall, Fire Station, and Police Station
- Including emergency operations center
- Community learning center for Inservice training, CPR, CERT, and public meetings
- The 2-story building efficiently collocates and stretches resources to enhance public safety
- Design (SD): 12/07/21 – 11/07/22
- Site Development Construction: 10/01/22 to 12/3/22
- Building Construction 03/02/23 – 05/16/24
- Final Completion 05/16/24
Current Activities
Construction
The contractor continued to make progress during the month of April. They have paved the north parking area that will house Phoenix Police Department’s squad cars, as well as provide entry and exit for the Phoenix Fire District engines. The contractor has also completed the department siding at the Police and Fire departments. April saw a grand coordination event with the delivery and installation of the facilities furniture, fixtures, and equipment. This effort provided each department with their office furniture. Following the furniture installation, critical punch list walks were conducted to catch remaining defects in finishes and contract work. The contractor made strides toward commissioning with the startup of equipment and troubleshooting for appropriate office conditions. Additional concrete sidewalks and landscaping was completed as well at the facility to tie in exterior finishes
Activities Scheduled for Next Period
- Continue installation of finishes throughout the building
- Internet and Phone line service installations
- Installation of apparatus bay doors
- Commissioning of equipment
Highlights/Challenges
- Installation of FFE
- Completion North parking lot
- Completion of preliminary punch walk
- Testing for HVAC systems
- Siding at Police and Fire
- Police Lobby stairs
- Continue working through the schedule impact with Adroit due to labor strike delaying exterior rockwool insulation.